EnerGulf has achieved the following milestones concerning its Lotshi Block work program:
- surveyed the true boundaries of the block and gained government approval
- acquired an aeromagnetic and gravity survey of the block
- completed and received its government certification of its Environmental Impact
Study required for operations on the block
- received its Exploration Permit from the government
- reprocessed and evaluated over 300 sq. km of existing 2D seismic data utilizing
state of the art processing
- organized its office and operations in the field to conduct the seismic program
- has secured various necessary equipment for the operation
- performed dynamite testing
- built and completed its base camp for seismic operations
- completed its demining assessment
- planned the lines for the seismic program
- conducted meetings to coordinate with the local authorities and population.
- the company has improved much of the road network in and around the block for better access to the seismic lines.
- to date, 40% of the program’s planned seismic lines have been cleared and surveyed